MobileESS
The Enico All-in-One mobile energy storage solution enables fast and easy use of renewable energy, regardless of location.
Mobile Energy Storage Systems
- Displaces the use of diesel generators on construction sites
- No need for major excavation work and opening of streets to build a large electricity connection to the construction site (cost savings)
- Reduces the size of the electrical connection on the construction site when used for peak shaving of max. electricity consumption (cost savings)
- Enables the construction of temporary electric car charging stations for the duration of the construction site.
- Emission-free temporary electricity distribution at events, fairs, festivals, etc.
- Localized grid support for areas where seasonal or temporary grid support is required
ENICO EnergyShare EV
Enico’s EnergyShare EV concept enables the construction of a full-scale charging station solution almost anywhere with a 400 VAC / 50 Hz electrical connection. At the heart of the EnergyShare EV is Enico’s unique MobileESS-EV energy storage system, which integrates 2 CCS power charging stations. In addition, the energy storage has several ready-made connection points for smaller 22 kW Type-2 AC charging units.
The solution makes it possible to set up extensive electric vehicle charging station infrastructure in locations such as construction sites, ski resorts, campsites or anywhere where it is not profitable to build a permanent charging station due to low/high seasonal usage or lack of electric network capacity.
MobileESS EV
Energy storage is increasingly being considered as a solution for the charging of electric vehicles in areas with limited grid capacity, or at charging stations where a large number of high-speed –chargers – 50 kW or more – are to be installed.
Typically, under these conditions, upgrading the regional power grid would be very expensive. At these sites, installing an energy storage to balance the load of electricity is a great solution.
Enico has taken this thinking even further. What if you could build a full-service electric vehicle charging station solution anywhere in less than a day?
Technical
- Continous Power: 300kW
- Nominal Energy: 416kWh
- Transportable: Certified according UN38.3
- Commissioning time: Appr. 1 hour
- Connection to Grid: Can be connected to normal 400VAC/50Hz low voltage connection (min. 400VAC/32A, limited min. use 16A)
- Includes: 2 pcs 120kW CCS charging stations
- Includes: 4pcs feeds for 8 pcs AC-chaging stations Type-2 AC-charging units
Applications
- Allows Removable EV charging infrastructure (Peak Shaving)
- Grid Frequency Regulation: FCR-N or FFR by using Virtual Power Plant Service Platform (Optional).
MobileESS CI
Electricity is one of the most important factors in all construction projects.
All construction projects require electricity to operate a variety of machines on the construction sites. Reliable access to electricity is a requirement in all construction projects. In many cases, construction sites depend on diesel-powered generators to obtain the required electrical power as the main electrical connection on the site is often unable to provide enough power.
For example, tower cranes, earthmoving machinery, material handling equipment, road construction machinery and concrete equipment are all part of construction activities that have a high electric power demand. Furthermore, the electrification of construction machinery will significantly increase the need for electricity on construction sites.
Technical
- Continous Power: 300kW
- Nominal Energy: 416kWh (version CI), 624kWh (version CI L)
- Transportable: Certified according UN38.3
- Commissioning time: Appr. 1 hour
- Connection to Grid: Can be connected to 400VAC/50Hz low voltage switchgear (min. 400VAC/32A, limited min. use 16A)
- Integrated 400VAC/500A single line High-Current connectors, and a 400VAC/400A unit output
- CEE Plug-in receptacles: 2pcs 400VAC/125A, 2pcs 400VAC/63A, 2pcs 400VAC/32A, 2pcs 400VAC/16A, and 3pcs Schuko-type receptacles 230VAC/16A
Applications
- Back-Up power supply (Islanding)
- Replaces diesel generators eg. In construction sites (Peak Shaving)
- Grid Frequency Regulation: FCR-N or FFR by using Virtual Power Plant Service Platform (Optional).
ENICO EnergyShare CI
Enico’s unique EnergyShare concept is an emission-free, environmentally friendly and efficient alternative to polluting fossil fuel-consuming generators that are commonly used for peak power distribution in construction projects.
At the heart of the EnergyShare solution is Enico’s unique MobileESS CI energy storage system. MobileESS CI is a movable and extremely versatile energy storage device optimized for the construction site environment.
The MobileESS CI mobile energy storage unit can be used to implement high-efficiency electrical energy distribution throughout the construction site, regardless of the size of the site’s main electric supply.
Best of all, an energy storage system offers electrical energy costs that are up to 5-6 times cheaper than producing the same amount of electrical energy with a diesel generator. In addition, the carbon footprint of the energy storage system is up to 8 times smaller than that of a diesel generator of the same electrical power.